Construct a gross material requirements plan.
The demand for subassembly S is 110 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 1 week to make Z.
Construct a gross material requirements plan.